Reporting Completed and Moved Quantities to Jobs that Have Not Started
Use this form to report completed and moved quantities for jobs that have not started. Using the End Run Only form allows you to start and stop a job in a single transaction. When you report quantities to a job using this form, a job stop transaction will be recorded at the current time, and a job start transaction will be generated to occur immediately following your most recent transaction. For example, if you clock in at 8:00 and stop job ABC at 9:00, a start job transaction for job ABC will be generated at 8:00. Then, if you stop job XYZ at 11:00, a start job transaction for job XYZ will be generated at 9:00.
The End Run Only parameter must be selected for the End Run Only form to be used. The End Run Only form is only available if Infor Time Track is implemented.
To stop jobs that have started, use the End Run form or the Work Center form.
To report completed and moved quantities to job operations that have not started: