Cost to Complete Log Report

Use this form to view a history of project costs organized by task and by cost code within task. For each cost code item, the report shows actual cost incurred to date, forecast cost, and the expected cost to complete the item (forecast cost minus actual cost). The report shows similar total amounts by cost class (labor, material, and other) in each task and total amounts for the entire task as well as for the project.

Note:  The report is drawn from data in the Project Cost to Complete Log. Before generating a report, run the Cost to Complete Snap Shot activity, which copies cost data to the log.