Budget vs Actuals by Project/ Activity/ Cost Component

The Budget vs Actual by Project/ Activity/ Cost Component report displays the actual cost against the available budget for the project, at the cost component level.

To generate the report, specify:

  • Company

    The code of the company.

  • Currency Type

    The type of the currency used for the project.

  • Project

    The code of the project for which the report is generated.

  • Activity

    The activity linked to the project.

The report displays this data:

  • Cost Component

    The cost component linked to the project.

  • Currency

    The project currency.

  • Budget

    The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).

  • Actual Cost

    The actual cost incurred on the project.

  • Balance Budget
    • Amount

      The balance amount calculated using the formula:

      (Budget - Actual Cost)

    • %

      The balance amount expressed as a percentage:

      ((Budget - Actual Cost)/ Budget))*100