Budget vs Actual Hours by Project

The Budget vs Actual Hours by Project report displays the planned hours against the actual hours of the project, for the available budget.

Select the required project and click Budget vs Actual Hours by Project/ Activity to view the report.

To generate the report, specify:

  • Company

    The code of the company.

  • Project

    The code of the project for which the report is generated.

  • Status

    The project status.

  • Acquiring Method

    The method used to acquire the project.

  • Financing Method

    The financing method used for the project.

  • Business Sector

    An area of commercial endeavor. Projects can be categorized based on the business sector.

  • Geographical Area

    The geographical area associated with the project.

  • Category

    The user-defined classification of the project.

  • Group

    The user-defined classification of the project.

  • Program

    A group of related projects managed in a coordinated way to obtain more benefits and control.

  • Project Manager

    The employee who manages the project.

The report displays:

  • Project

    The code of the project for which the report is generated.

  • Planned Hours

    The budgeted hours required for the completion of the project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).

  • Actual Hours

    The actual hours utilized for the completion of the project.

  • Balance Hours

    The balance hours calculated using the formula:

    (Planned Hours - Actual Hours)

  • Budget %

    The balance hours expressed as a percentage:

    ((Planned Hours - Actual Hours)/ Planned Hours))*100