Budget vs Actuals by Project/ Activity

The Budget vs Actual by Project/ Activity report displays the actual cost against the available budget for the project, at the activity level.

Select the required activity and click Budget vs Actual by Project / Activity / Cost Component or Budget vs Actual by Project / Activity / Control Code to view the report for:

  • The budget vs actual data at the project/ activity/ cost component level
  • The budget vs actual data at the project/ activity/ control code level

To generate the report, specify:

  • Company

    The code of the company.

  • Currency Type

    The type of the currency used for the project.

  • Project

    The code of the project for which the report is generated.

The report displays:

  • Activity

    The activity linked to the project.

  • Status

    The status of the budget.

  • Currency

    The project currency.

  • Budget

    The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).

  • Actual Cost

    The actual cost incurred on the project.

  • Balance Budget
    • Amount

      The balance amount calculated using the formula:

      (Budget - Actual Cost)

    • %

      The balance amount expressed as a percentage:

      ((Budget - Actual Cost)/ Budget))*100