Budget vs Actuals by Project

The Budget vs Actual by Project report displays the actual cost against the available budget for the selected project.

Select the required project and click Budget vs Actual by Project/ Activity to view the report.

To generate the report, specify:

  • Company

    The code of the company.

  • Currency Type

    The type of the currency used for the project.

  • Project

    The code of the project (range) for which the budget report is generated.

  • Status

    The project status.

  • Acquiring Method

    The method used to acquire the project.

  • Financing Method

    The financing method used for the project.

  • Business Sector

    The area of commercial endeavor. Projects can be categorized based on the business sector.

  • Geographical Area

    The geographical area associated with the project.

  • Category

    The user-defined classification of the project.

  • Group

    The user-defined classification of the project.

  • Program

    A group of related projects managed in a coordinated way to obtain more benefits and control.

  • Project Manager

    The employee who manages the project.

  • Actual Cost

    Actual Cost = Actual Cost + Hard Commitment

    or

    Actual Cost = Actual Cost + Hard Commitment + Soft Commitment

The report displays:

  • Project

    The code of the project for which the report is generated.

  • Currency

    The project currency.

  • Budget

    The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).

  • Actual Cost

    The actual cost incurred on the project.

  • Balance Budget
    • Amount

      The balance amount calculated using the formula:

      (Budget - Actual Cost)

    • %

      The balance amount expressed as a percentage:

      ((Budget - Actual Cost)/ Budget))*100