Budget vs Actuals by Project
The Budget vs Actual by Project report displays the actual cost against the available budget for the selected project.
Select the required project and click Budget vs Actual by Project/ Activity to view the report.
To generate the report, specify:
- Company
The code of the company.
- Currency Type
The type of the currency used for the project.
- Project
The code of the project (range) for which the budget report is generated.
- Status
The project status.
- Acquiring Method
The method used to acquire the project.
- Financing Method
The financing method used for the project.
- Business Sector
The area of commercial endeavor. Projects can be categorized based on the business sector.
- Geographical Area
The geographical area associated with the project.
- Category
The user-defined classification of the project.
- Group
The user-defined classification of the project.
- Program
A group of related projects managed in a coordinated way to obtain more benefits and control.
- Project Manager
The employee who manages the project.
- Actual Cost
Actual Cost = Actual Cost + Hard Commitment
or
Actual Cost = Actual Cost + Hard Commitment + Soft Commitment
The report displays:
- Project
The code of the project for which the report is generated.
- Currency
The project currency.
- Budget
The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).
- Actual Cost
The actual cost incurred on the project.
- Balance Budget
- Amount
The balance amount calculated using the formula:
(Budget - Actual Cost)
- %
The balance amount expressed as a percentage:
((Budget - Actual Cost)/ Budget))*100
- Amount