Budget vs Actual Hours by Project/ Activity/ Control Code
The Budget vs Actual Hours by Project/ Activity/ Control Code report displays the planned hours against the actual hours of the project for the available budget, at the control code level.
To generate the report, specify:
- Company
The code of the company.
- Project
The code of the project for which the report is generated.
- Activity
The activity linked to the project.
The report displays:
- Control Code
The control code linked to the project.
- Planned Hours
The budgeted hours required for the completion of the project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).
- Actual Hours
The actual hours utilized for the completion of the project.
- Balance Hours
The balance hours calculated using the formula:
(Planned Hours - Actual Hours)
- Budget %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours))*100