Cost Components Trend
You access this report by clicking the Trend tab in the Cost Variances by Cost Components report.
The report shows the trend of costs of each cost component for the previous three months.
To select the periods on which to report, click the settings button and select
.SeeTime Settings.
To analyze cost trend by workcenter or by Items, click the settings button in the table heading and select
or .You can filter the report by these criteria:
- Workcenter
- Product
- Cost type
A bar chart compares the actual and planned costs of selected cost components.
By default, the data table and chart display the values for these cost components:
- Material
- Machine
- Labor
- Contractor
- Burden
These are the linked reports:
- Order Costing KPI Trend. Click a Item or workcenter in the data table and select the report.
- Cost Variances by Cost Components. Click the Cost Components tab.
- Cost Components Actual vs. Standard. Click the Actual vs. Standard tab.
- Cost Components Actual vs. Planned. Click the Actual vs. Planned tab.