Production dashboard
The Production dashboard displays key manufacturing metrics in six panes.
In the Settings dialog you can specify, for example, the reference date for the dashboard, and the accounting entity, unit and order type for which to view data.
See Settings.
- Machine and Labor Time in previous month
-
Bar charts compare the actual to the planned machine time, and the actual to the planned labor time.
- These are the linked reports:
- Machine and Labor Time Comparison
- Machine and Labor Time Trend
- Machine and Labor Time Trend Detail
- Operation Analysis KPI Dimension Analysis
- Operation Analysis KPI Trend
- Punctuality
- A bar chart displays the percentage of orders during the previous month that were late, on time, or early.
- These are the linked reports:
- Punctuality Single Period
- Punctuality Trend
- Punctuality Cluster
- Punctuality Cluster Trend
- Operation Analysis KPI Dimension Analysis
- Manufactured Quantity in Last 5 months
- A column chart compares the planned and actual quantities of manufactured items over the five months prior to the current month. A trend line represents the reject percentage.
- These are the linked reports:
- Manufactured Quantities Trend
- Manufactured Quantities Comparison
- Rejects by Workcenter Comparison
- Rejects by Workcenter Trend
- Rejects by Phantom Items Comparison
- Rejects by Phantom Items Trend
- Operation Analysis KPI Trend
- Operation Analysis KPI Dimension Analysis
- Durations in Last 5 months
- A column chart compares the planned hours with the actual hours over the five months prior to the current month. A trend line represents the percentage of overruns during the period.
- These are the linked reports:
- Duration Trend
See Duration Trend
- Duration Comparison
- Operation Analysis KPI Trend
- Operation Analysis KPI Dimension Analysis
- Duration Trend
- Cost Components - Actual vs. Estimated
- A bar chart compares actual material, machine, labor, contractor, and burden costs with their planned costs.
- These are the linked reports:
- Cost Variances by Cost Components
- Cost Components Trend
- Cost Components Actual vs. Standard
- Cost Components Actual vs. Planned
- Cost Components
- A bar chart shows the variances between actual and planned component costs for the previous month and the year to date.
- These are the linked reports:
- Cost Components Actual vs. Planned
- Cost Components Actual vs. Standard
- Cost Components Trend
- Cost Variances by Cost Components