Distributing Process Batches - Options Tab
- In the planning board, select process batches.
-
Select
Schedule > Distribute
Process Batches.
The Distribute Process Batches dialog box is displayed.
- Click the Options tab.
-
If you want splitting to take place when a batch coincides with
any of these items, select the
time period where resource is
unavailable,
downtime, and
locked and unselected
batches check boxes.
Clearing these check boxes can lead to batch overlap.
- If you want that the batches be split at the maximum batch duration of the resource, select maximum duration.
-
If you want to allow process batches to be joined, perform these
operations:
- Select the with joining check box.
-
To join overlapping batches as adjacent batches, select
adjacent only and
choose one of these options:
- adjacent if within
- To join overlapping batches, select this option and specify the overlapping interval.
- adjacent if successive
- To join only successive batches, select this option.
- To join linked batches only, select linked only.
- To join only batches that use the same resource, select on same resource only.
-
To join batches together in a period, select
use cycle and select a
cycle.
If you select this checkbox, the batches that belong to the same cycle period are joined.
-
To join batches on fields of any related order, select
if field values are the
same and select a field.
The search method for the related order is the same as for any related order in the interfaces. If several orders are connected, the first order that is filled by the selected batch is considered only.
- To view the change results in the planning board, click Apply.
- Click OK. Alternatively, continue populating tabs on this window.