Allocating Resources

To allocate the resources:

  1. Select the required Process batches and Tank batches on the planning board.
  2. Select Schedule > Allocate. The Allocate dialog box is displayed.
  3. Enable or disable these options as required:
    • extend selection: To extend the selection to all the batches within the working area on the resource groups of the selected batches.
    • keep allocation: To prevent reallocation of the Process batches or Tank batches. Only Enabling batches are reallocated.
    • keep enabling allocation: To prevent reallocation of the Enabling batches. Only Process batches and Tank batches are reallocated.
  4. Click Apply. You can preview the changes you have made, on the planning board.
  5. Click OK to accept the changes. Else click Cancel.