Specifying the requirement information for the shipper
Use this page to specify the requirement information, ship coverage, transit time, dock and purchase order number for the shipper. Some of the information is displayed based on the values specified on the Shipper page.
To specify the requirement information:
- Select Shipments > Create Shipper. The Shipper page is displayed.
- Specify the required information.
- Click Continue. The Requirements page is displayed.
-
Review this information:
- Facility
- The name of the location from where the demand for the parts is raised.
- Ship To
- The location to which the parts are shipped.
- Supplier
- The name of the supplier.
- Ship From
- The location from where the parts are shipped.
- Shipper Number
- The code of the shipper.
-
Specify this information:
- Dock
- The code of the dock to which the shipment is sent.
- Test or Production
- The option to indicate the type of the
requirement. Possible values:
- Test: This value indicates the test requirement, as defined by the customer. Typical test requirements include a trial run with no production or shipment of the part.
- Production: This value indicates that the part must be produced and shipped.
- Requirement View
- The number of days within which requirements must be due for them to display on the Add Line Item page. The Requirement view must be larger than the Ship Coverage so you can view demand due within a longer period of time than the demand you plan to ship against.
- Ship Coverage
- The number of days within which demand must be due for it to be included in the recommended ship quantity. Only demand that is due within the Ship Coverage displays in the Parts to Ship table on the Requirement Filter page. The parts selected in the Parts to Ship table will appear as line items on the shipper. On the Add Line Item page, the ship quantity for the selected part defaults based on the Ship Coverage. The Ship Coverage must be less than the Requirement View.
- Include Weekends
- If this check box is selected, the Ship Coverage considers the weekend days. For example, if the current day is a Friday and the Ship Coverage is specified as 2 then the requirements for Friday and Saturday are included.
- Transit Time
- The time required for the shipment to reach the
Ship To location.
Note: This value is defaulted from the Ship From page.
- PO Number
- The purchase order (PO) number associated with the requirements.
- Click Search.
- Select the Part and the corresponding quantity for which the shipper must be created.
- Click Create Shipper.