Overall Project Performance
This is a traffic light based metric that provides a graphical view of the overall performance of the project.
Traffic Light Indicators:
- Green
Project is on Schedule.
- Yellow
Project requires attention.
- Red
Project requires immediate attention
Indicator | Effort | SPI | CPI | VAC | OTP |
---|---|---|---|---|---|
(Earned Value hours - Actual Hours)/Earned Value * 100 | Earned Value/Planned Value | Earned Value / Actual Cost | (Budget at Completion – Estimate at completion)/Budget at Completion * 100 | No. of activities completed till date / No. of activities planned to be completed as on date | |
Green | > = 0 | >= 1 | >= 1 | >=0 | >= 1 |
Yellow | = -5 to 0 | =0.95 to 0.99 | =0.95 to 0.99 | = -5 to -0.009 | = 0.95 to 0.99 |
Red | < -5 | < 0.95 | < 0.95 | < 0 | < 0.95 |
Note:
- Effort is not specified if Earned Value is zero.
- SPI is not specified if budget (planned value) is defined for the project.
- CPI is not specified if Actual Cost is not yet booked for the project (or booked with zero cost).
- VAC is not specified if budget is not defined for project.
- OTP is not specified if activity is not completed.
The indicators list additional information for each metric:
- Click Effort to view the Effort by Project.
- Click SPI to view the Earned Value by Project.
- Click CPI to view the Earned Value by Project.
- Click VAC to view the Estimate at Completion by Project.
- Click OTP to view the Activity Performance of the project.
- You can view the CPI/ SPI Trend by Project from Earned Value by Project which can be accessed using CPI or SPI.