Milestone Performance
When the user clicks
, the Activity Performance is displayed. However, the user can view another metric Milestone Performance using the toggle option. These metrics indicate the progress of the activities or milestone according to the defined baseline plan. Milestone Performance is calculated based on the total number of milestones actually completed as compared to the number of milestones planned to be completed, periodically. Future period plan is displayed as a dotted curve.You can also view the Activity Performance using the Toggle option.