Finish Variance

This bar metric displays the baseline finish date versus the expected finish date. A positive difference between the expected finish date and the baseline finish date indicates an issue with the progress of the project. The project manager can investigate the issues and identify the reasons, based on which corrective actions can be initiated.

Finish Variance = Expected Finish Date - Baseline Finish Date

Note: Infor LN selects the baseline finish date from the latest Approved Baseline details, for the Top activity. The expected finish date is the scheduled finish date of the activity.