Time Phased Hours by Project/ Activity/ Control Code
The Time Phased Hours by Project/ Activity/ Control Code report displays the time phased budget data and the actual hours utilized for the project in the current and the cumulative periods, at the control code level. Time phasing is based on the Earned Value (EV) method, specified for the activity.
To generate the report, specify:
- Company
The code of the company.
- Project
The code of the project for which the report is generated.
- Activity (Description)
The activity linked to the project.
The report displays this data:
- Control Code (Description)
The control code linked to the project.
- Period/ Cumulative
- Year
The current/ cumulative year for which the report is generated.
- Period
The current/ cumulative period of the year for which the report is generated.
- Planned Hours
The estimated number of hours required for the completion of the project in the current/ cumulative period. Calculations are based on the Earned Value (EV) method, defined for the activity.
- Actual Hours
The actual hours used to complete the project in the current/ cumulative period.
- Balance Hours
The balance hours in the current/ cumulative period, calculated using the formula:
(Planned Hours - Actual Hours)
- Balance Hours %
The balance hours expressed as a percentage:
((Planned Hours - Actual Hours)/ Planned Hours) * 100
- Year