Hours Forecast by Project/ Activity/ Control Code

The Hours Forecast by Project/ Activity/ Control Code report allows the project manager to analyze the planned hours, the actual hours utilized to complete the project and determine the variance; at the control code level.

Note: 
  • The hours forecast report at the control code level is displayed only for the cost type, Labor.
  • Generate and approve the forecast (in Infor LN) of all the budget lines in Infor LN, for an optimal BI forecast.

To generate the report, specify:

  • Company

    The code of the company.

  • Project

    The code of the project for which the report is generated.

  • Activity (Description)

    The activity linked to the project.

The report displays this data:

  • Control Code (Description)

    The control code linked to the project.

  • Planned Hours

    The budgeted number of hours required for the completion of the project.

  • Actual Hours

    The actual number of hours utilized to complete the project.

  • Forecast
    • Estimate to Complete

      The estimate to complete is the additional cost incurred for an activity or a project.

      (Estimate To Complete = Estimate At Completion - Actual Cost)

    • Estimate at Completion

      The estimate at completion is the total cost incurred for an activity or a project.

    • Variance at Completion

      Variance at Completion is the difference between the budgeted amount and the estimated amount, at the end of the project.

      Variance at Completion = Budget - Estimate at Completion