Hours Forecast by Project/ Activity
The Hours Forecast by Project/ Activity report helps the project manager to analyze the planned hours, the actual hours utilized to complete the project and determine the variance; at the activity level.
Select the required activity to view the hours forecast data of the project at the project/ activity/ control code level
To generate the report, specify:
- Company
The code of the company.
- Project
The code of the project for which the report is generated.
The report displays this data:
- Activity (Description)
The activity linked to the project.
- Progress %
The progress data populated from Infor LN.
- Planned Hours
The budgeted number of hours required for the completion of the project.
- Actual Hours
The actual number of hours utilized to complete the project.
- Forecast
- Estimate to Complete
The estimate to complete is the additional cost incurred for an activity or a project.
(Estimate To Complete = Estimate At Completion - Actual Cost)
- Estimate at Completion
The estimate at completion is the total cost incurred for an activity or a project.
- Variance at Completion
Variance at Completion is the difference between the budgeted amount and the estimated amount, at the end of the project.
Variance at Completion = Budget - Estimate at Completion
- Estimate to Complete