Project Performance by Project/ OBS

The Project Performance by Project/ OBS report displays the performance indices of the project. These are calculated using the earned value and the variance data of the project for the current and cumulative periods, at the organization breakdown structure level.

To generate the report, specify:

  • Company

    The code of the company.

  • Project

    The code of the project (range) for which the report is generated.

  • Currency Type

    The type of the currency based on which the report is generated.

  • Period (Monthly)

    The period (range) of the year for which the report is generated.

The report displays this data:

  • OBS (Description)

    The organization breakdown structure linked to the project.

  • Currency

    The currency in which the report data is displayed.

    Note: This value is based on the selected Currency Type.
  • Period/ Cumulative
    • Year

      The current/ cumulative year for which the report is generated.

    • Period

      The current/ cumulative period of the year for which the report is generated.

    • Planned Value

      The amount of work planned in the current/ cumulative period. The Bottom-up budget specified in Infor LN. This budget is Time Phased based on the Earned Value Method of the activity.

    • Earned Value

      The amount of work completed in the current/ cumulative period.

    • Actuals

      The actual cost incurred for the task in the current/ cumulative period.

    • Cost Variance

      The difference between the estimated cost and the actual cost incurred for the task.

      Cost variance = Earned value - Actuals

    • Schedule Variance

      The time period by which a project is ahead of or behind the schedule.

      Schedule variance = Earned value – Planned value

    • Cost Performance Index

      The cost performance index is calculated by dividing the earned value with the actual cost.

    • Schedule Performance Index

      The schedule performance index is calculated by dividing the earned value with the planned value.

EV Method in Infor LN EV Calculation is based on
Percent Complete Progress defined in Infor LN for the activity
Start and End Percent Start and end date of the activity
Milestone Milestone completion date
Level of Effort Effort to complete the project
Apportioned Distribution of the Earned value