Project Performance by OBS/ Project
The Project Performance by OBS/ Project report displays the performance indices. These are calculated using the earned value and the variance data for the current and cumulative periods. This report analyze the earned value by OBS and by Projects linked to it.
To generate the report, specify:
- Currency Type
The type of the currency used for the project.
- Company
The code of the company.
- OBS
The code of the OBS Structure for which the report is generated.
- Period
The period (range) of the year for which the report is generated.
- Actual Cost
Actual Cost = Actual Cost + Hard Commitment, Actual Cost = Actual Cost + Hard Commitment + Soft Commitment
The report displays this data:
- Project
The code of the project for which the report is generated.
- Currency
The currency in which the report data is displayed.
Note: This value is based on the selected Currency Type. - Budget
The budget allocated to the selected project. The Bottom-up budget specified in Infor LN (all budgets are considered irrespective of the status).
- Period/ Cumulative
- Year
The current/ cumulative year for which the report is generated.
- Period
The current/ cumulative period of the year for which the report is generated.
- Planned Value
The amount of work planned in the current/ cumulative period. The Bottom-up budget specified in Infor LN. This budget is Time Phased based on the Earned Value Method of the activity.
- Earned Value
The amount of work completed in the current/ cumulative period.
- Actuals
The actual cost incurred for the task in the current/ cumulative period.
- Cost Variance
The difference between the estimated cost and the actual cost incurred for the task.
Cost variance = Earned value - Actual Costs
- Schedule Variance
The time period by which a project is ahead of or behind the schedule.
Schedule variance = Earned value – Planned value
- Cost Performance Index
The cost performance index is calculated by dividing the earned value with the actual cost.
- Schedule Performance Index
The schedule performance index is calculated by dividing the earned value with the planned value.
- Year
EV Method in Infor LN | EV Calculation is based on |
---|---|
Percent Complete | Progress defined in Infor LN for the activity |
Start and End Percent | Start and end date of the activity |
Milestone | Milestone completion date |
Level of Effort | Effort to complete the project |
Apportioned | Distribution of the Earned value |