Budget vs Actuals by Project/ Element/ Control Code
The Budget vs Actual by Project/ Element/ Control Code report displays the actual cost against the available budget for the project, at the control code level.
To generate the report, specify:
-
Company
The code of the company.
-
Currency Type
The type of the currency used for the project.
-
Project
The code of the project for which the report is generated.
-
Element
The element linked to the project.
The report displays:
-
Control Code
The control code linked to the project.
-
Currency
The project currency.
-
Budget
The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).
-
Actual Cost
The actual cost incurred on the project.
- Balance Budget
-
Amount
The balance amount calculated using the formula:
(Budget - Actual Cost)
-
%
The balance amount expressed as a percentage:
((Budget - Actual Cost)/ Budget))*100
-
Amount