Budget vs Actuals by Project/ Element
The Budget vs Actual by Project/ Element report displays the actual cost against the available budget for the project, at the element level.
Select the required element and click Budget vs Actual by Project / Element / Cost Component or Budget vs Actual by Project / Element / Control Code to view the report for:
- The budget vs actual data at the project/ element/ cost component level
- The budget vs actual data at the project/ element/ control code level
To generate the report, specify:
-
Company
The code of the company.
-
Currency Type
The type of the currency used for the project.
-
Project
The code of the project for which the report is generated.
The report displays:
-
Element
The element linked to the project.
-
Status
The status of the budget.
-
Currency
The project currency.
-
Budget
The budget allocated to the selected project. This is the Bottom-up budget specified in Infor LN (all budgets are considered, irrespective of the status).
-
Actual Cost
The actual cost incurred on the project.
- Balance Budget
-
Amount
The balance amount calculated using the formula:
(Budget - Actual Cost)
-
%
The balance amount expressed as a percentage:
((Budget - Actual Cost)/ Budget))*100
-