Machine and Labor Time Trend Detail

You access this report from the Machine and Labor Time Trend or the machine and Labor Time Comparison report or report by clicking a Item or workcenter in the report and selecting Machine and Labor Time - Trend Detail from the menu.

See these topics:

Machine and Labor Time Trend

Machine and Labor Time Comparison

The report compares the actual machine time and labor time required to manufacture a selected Item or Item group to the planned machine and labor time.

The report displays two column charts. For a selected Item and workcenter, one chart compares the planned labor time to the actual labor time. The second chart compares the planned machine time to the actual machine time.

For both machine hours and labor time, the data table displays the actual time and planned time for the selected periods, and the variances between them as absolute values and as percentages.

To display data for different, or further periods, click the settings icon in the table heading and select Time Settings.

See Time Settings.