Duration Trend

You access this report by clicking the heading of the Durations metric in the Production Dashboard or by clicking the Trend tab in the Duration Comparison report.

Duration Comparison.

You can report on the duration trend by Item or the duration trend by workcenter by exchanging the positions of the Product and Workcenter dimensions. To exchange the dimensions, click the double arrows in the table heading. To report, for example, on the trend by workcenter, place the workcenter dimension at the left. To report on the trend by Item, place the Item dimension at the left.

A column chart compares the actual duration to the planned duration. A trend line represents the overrun percentage over the selected periods.

By default the report compares data for the base period selected in the Production dashboard.

See Production dashboard.

To compare different periods, click the settings icon in the table heading and select Edit time settings.

See Time Settings.

The data table shows the values for a selected measure of duration over the previous five months, for a selected Item or workcenter.
Note: Measures and KPIs that relate to durations and punctuality are mapped to a single work center, even if several work centers are involved in the Itemion process. In each case, the measures are mapped to the work center that is responsible for the final operation in the process. This is not necessarily the work center that is responsible for, for example, an issue highlighted by the report.
Select one of these measures from the Measure list:
  • Duration estimated
  • Duration actual
  • Lead time variance
  • Lead time ratio
  • Overrun percentage
  • Overrun

Expand elements in the data table to drill down the workcenter and Item hierarchies. To compare the planned and actual durations, and to see the overrun percentage trend, click an element of the left hand dimension in the data table and select Show in chart.

For each Item and workcenter, a sparkline represents the trend of the selected measure over the selected period. If a Item is a base element, its Base Unit of Measure is displayed.

This report is also available as a comparison analysis which compares the planned and actual durations of Itemion orders. Click the Comparison tab to display the Duration Comparison report.

See Duration Comparison.