Variance at Completion
The Variance at Completion bar chart displays the variance at completion for all the projects assigned to a project manager. A negative variance at completion indicates a cost overrun. A positive variance at completion indicates a cost deficit. See Estimate at Completion
Variance at Completion (VAC) value = Budget at Completion (BAC) - Estimate at Completion (EAC).