Project Scheduling
The project schedule status allows the project manager to track the project schedule and identify variances for the project, if any. The report allows you to review the project performance with respect to the schedule adherence.
To view the report, specify:
- Company
The code of the company.
- Project
The code of the project for which the report is generated.
- Baseline ID
The ID of the approved project baseline.
- Baseline Execution Index
A measure of baseline execution of the project.
BEI = no. of milestones completed till a period / no. of milestones planned to be completed till a period
- Milestone Execution Index
A measure of milestone execution of the project.
The report displays this data:
- Activity (Description)
The activity linked to the project.
- Type
The type of the activity.
- Duration (Days)
The duration of the activity in the project.
- Baseline Start Date
The start date of the activity, as specified in the baseline.
- Actual Start Date
The date when the activity is started.
- Expected Finish Date
The date when the activity is expected to finish. This date can be different from the Base Line Finish date.
- Actual Finish Date
The date when the activity is completed.
- Start Variance
The number of days by which the activity starts prior to or later than the planned date.
Start Variance = Baseline Start Date - Actual Start Date
- Finish Variance
The number of days by which the activity is expected to finish prior to or later than the planned date.
Finish Variance = Baseline Finish Date - Expected Finish Date