Overall Contract Performance

The Contract Overall Performance chart is a traffic light based metric that provides a graphical view of the overall performance of the contract.

Traffic Light Indicators:

  • Green

    Contract is profitable.

  • Red

    Contract incurs loss.

The table provides these indices:
Current Profit Expected Profit Overdues
Green > = 0 > = 0 No
Red < 0 < 0 Yes
  • Current Profit = Revenue Recognized – Cost of Sales
  • Expected Profit = Sum of all Contract Line Amounts – Estimated Budget at Completion
  • Revenue Recognized = Sum of all the Interim Revenues Results by contract line
  • Cost of Sales = Sum of all the Interim Costs Results by contract line
  • Contract Amount = Sum of all the contract line amounts
  • Estimated Budget At Completion (EAC) = Sum of all the EAC amounts for the projects linked to the contract line