cost performance index

A measure of cost efficiency of a project.

The cost performance index (CPI) is determined by measuring the ratio of earned value (EV) to actual costs (AC):

CPI = EV / AC

If the result is less than 1.0, cost is greater than budgeted.

If the result is greater than 1.0, cost is less than budgeted.

example:

EV PV AC CPI SPI
270 335 250 1.08 0.81