Production Settings by Site (timfc0180m000)

Use this session to manage item production settings by site.

This session contains data from the following parameter sessions:

You can specify parameter settings specific to a site or the whole company, which can be enabled using the Use Global Repetitive Parameters, Use Global Production Order Parameters, Use Global Assembly Control Parameters, Use Global Tool Planning Parameters check boxes available in this session.

Note: This session is only accessibly if the multisite functionality is activated.

Field Information

Site
Site

The site where production takes place.

Address

address

Logistic Company

logistic company

External

the planning cluster is linked to subcontractor sites or the planning cluster is used in planning for VMI Forecast.

This depends on the settings of these check boxes:

  • Holds Subcontractor Sites
  • Customer Site

Determining the VMI Relation

Job Shop
Text

additional text is present.

Use Global Master Data Parameters

the global job shop parameters are used for the site. Consequently, changes to product data at company level are synchronized automatically to site level.

Operation Rates
Operation Rate Currency

The currency automatically selected for the specified rates for the site.

Default Operation Rate Code
The operation rate code that is used as default for each costing work center.
Note: This field is displayed only if the Job Shop by Site field is set to Active in the Implemented Software Components (tccom0100s000) session.
Job Shop BOM
BOM Order Series

The model order series to which the bill of material belongs.

Allow Multiple Job Shop BOMs per Item and Site

multiple bills of material for the same item can be used for manufacture on the same site.

Note: Does not apply when the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session is not Active.
Routing
Use Site-specific Reference Operations Only

only reference operation linked to the site are used.

Default Job Shop Routing

The default routing for the specified site.

This routing is selected if:

  • The routing is independent of the order quantity.
  • No routing is defined for the required quantity.
Production Order
Text

additional text is present.

Use Global Production Order Parameters

the production order parameters are used for the site. Consequently, changes to production order parameters at company level are synchronized automatically to site level.

Production Order Series for Enterprise Planning

The default production order series that is used by Enterprise Planning when transferring orders to the execution level of LN.

Production Order Series for Order Grouping

The default series that is used to generate order group numbers in the Create Production Order Group (tisfc3250m000) session.

Production Orders

The default production order series that is used to generate production order numbers if you insert a production order manually in Job Shop Control .

Production Order Series for Planned Order Groups

Specify the first range of planned order groups that Enterprise Planning must transfer to the Job Shop Control module in Manufacturing .

Note: You cannot individually transfer a planned order that belongs to an order group, only the entire group.

Order grouping in Enterprise Planning

Scheduler
Production Scheduler

The activation status of the production scheduler.

Inactive

In Preparation

Active

Allow Ignoring Material Availability Constraints

the material availability check for selected purchase items for this site will be skipped during scheduling. The machine operation or operation that requires the selected material will start from the time fence date, with the restriction that the machine operation can't start before the preceding operations or orders are finished, and not before materials with availability restrictions are available.

Note: 
Sequencer
Order Block Sequencer

The activation status of the order block sequencer

Inactive

In Preparation

Active

Changeover Optimization
Changeover Optimization

changeover optimization is active.

Note: If the site has a machine capacity group which is changeover critical or the order block sequencer is In Preparation or Active, the changeover optimization parameter cannot be cleared.
Maximum Number of Setup Classes

Specify the maximum number setup classes that can be used in order block sequencing or job shop scheduling.

Note: 
  • For performance reason the maximum number of setup classes should be kept as low as possible.

  • The maximum allowed value is 3.

Maximum Number of Setup Class States

Specify the maximum number of setup class states that can be used in order block sequencing or job shop scheduling.

Note: 
  • For optimum performance the number of setup class states should be kept as low as possible.

  • The maximum number of setup class states allowed is 12.

Capacity Overview
Update Method Day Utilization

Select the method by which you want to rebuild day utilization, that is, to recalculate how much capacity per day is planned for work centers, machines, and so on.

Note: Not applicable if the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session is set to Active.

Allowed values

Automatic

The capacity is recalculated when you click Rebuild Capacity Utilization from the Utilization by Week (tisfc1502m000) session or the Utilization by Day (tisfc1503m000) session, or when the planning of orders is adjusted.

Manual

The capacity is recalculated when you run the Build Utilization (tisfc0201m000) session.

Not Implemented

The capacity is not recalculated.

Update Method Week Utilization

Select the method by which you want to rebuild week utilization, that is, to recalculate how much capacity per week is planned for work centers, machines, and so on.

Note: Not applicable if the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session is set to Active.

Allowed values

Automatic

The capacity is recalculated when you click Rebuild Capacity Utilization from the Utilization by Week (tisfc1502m000) session or the Utilization by Day (tisfc1503m000) session, or when the planning of orders is adjusted.

Manual

The capacity is recalculated when you run the Build Utilization (tisfc0201m000) session.

Not Implemented

The capacity is not recalculated.

Update Method I/O Control

The method for input/output control.

Allowed values

Day

When you generate input/output control data, the time bucket is one day. The start of the day is 00:00:00 and the end of the day is 23:59:59.

Not Implemented

Input/output control is not implemented and relevant sessions are disabled. This is the default setting.

Week

When you generate input/output control data, the time bucket is one week. The week start day is the company start day.

No. of Periods to Generate I/O Data

The period for which a work center's capacity and input/output values are calculated. Dependent on the value in the Update Method I/O Control field, the period is expressed in days or weeks.

Note: If you selected Not Implemented in the Update Method I/O Control field, you cannot enter a value in this field.

Input / output control

Include Partial Completions (Default)

LN also takes into account the routing operations that are reported only partially completed to calculate the input/output values.

LN only takes into account the routing operations that are reported entirely completed to calculate the input/output values.

You can select the Include Partial Completions (Default) check box if work centers are used for orders with extremely long lead times.

The setting of the Include Partial Completions (Default) check box works as a default for the Include Partial Completions (Default) check box in the Generate Work Center Input/Output Control (tisfc3210m000) session and the Generate Machine Input/Output Control Data (tisfc3220m000) session.

Input / output control

Combine Warehouse Orders End Item

If you report an end-item quantity as completed, you can choose to receive the end items in the warehouse immediately, or in a later stage. Usually, for every quantity that is received in the warehouse, a production warehouse order line is generated. If you receive the end items in the warehouse in a later stage, you can use this check box to combine production warehouse order lines, which limits database growth.

and you do not immediately receive the completed quantities in the warehouse, production warehouse order lines for the completed end-item quantities are combined into one production warehouse order line. As a result, the number of receipt transactions and variance transactions is reduced.

and you do not immediately receive the completed quantities in the warehouse, a production warehouse order line is created for every completed quantity.

Combine production warehouse order lines.

Text
Operation Text

Indicate the action to be performed to update the text for a routing operation.

Allowed values

Copy from Routing Operation
The text linked to the routing operation in the Routing Operations (tirou1102m000) session is copied to the production order in the Production Planning (tisfc0110m000) session. You can add or modify the routing operation text that is copied to the production order operation.
Link Routing Operation Text
The routing operation text in the Routing Operations (tirou1102m000) session is linked to the production order in the Production Planning (tisfc0110m000) session. You can specify operational text manually only after removing the link from the routing operation.
Material Text

Indicate the action to be performed for the Material line text of a new Production Order.

Allowed values

Copy from Bill of Material
The text from the Job Shop List of Material (tibom3110m000) session is copied to the Estimated Materials (ticst0101m000) session (which is part of the Production Order (tisfc0101m100) session). This option can be used when the text is expected to be changed on the production order.
Link Bill of Material Text
The text from the Job Shop List of Material (tibom3110m000) session is linked to the Estimated Materials (ticst0101m000) session. You can specify a new text on the production order, only after removing the link to the Job Shop BOM text.
Planning
Automatic Update Production Order Start Date

the production order start dates are automatically updated when the start or finish dates of the operations are modified. The production start date of the production order is then equal to the start date and time of the first operation's queue time.

This parameter only applies to the Production Start field.

Max. No. of Queue Time Compression Iterations

The number of times that LN repeats the queue time compression process until the production can be completed within the modified production order dates.

This parameter only applies if you selected the Best Fit method for queue time compression in the Automated Queue Time Compression (tisfc1103s000) session.

Queue time compression

Operation Numbering
Initial Value for Renumbering Operations

The operation number assigned to the first phantom routing operation that is added to the main item routing.

Default value

The default value is 100.

Renumbering phantom operations

Step Size for Renumbering Operations

The number by which each subsequent operation number is increased when phantom routing operations are added to the main item routing.

Default value

The default is 10.

Renumbering phantom operations

On Order Date Production Orders based on
Planned Receipt Date Method for On Time

The value of this field determines on which date the planned inventory transaction for a production order is based if the production order is expected to be delivered on time.

Note: The order is expected to be on time if the earliest finish date for the latest operation of the production order occurs before the delivery date for the production order.

Allowed values

Requested Order Delivery Date

The date on which the customer has requested delivery. LN equals the latest finish date of the latest operation with the Requested Order Delivery Date.

Planned Order Delivery Date

The (re)planned delivery date of the production order. This date equals the earliest finish date of the latest operation.

Planned Receipt Date Method when Late

The value of this field determines on which date the planned inventory transaction for a production order is based if the production order is expected to be delivered late.

Note: The order is expected to be late if the earliest finish date for the latest operation of the production order occurs after the delivery date for the production order.

Allowed values

Requested Order Delivery Date

The date when the order is created.

Planned Order Delivery Date

The (re)planned delivery date of the production order.

Reporting Complete
Reporting Method for Previous Operations

This parameter determines what happens if you report a quantity as complete for an operation, and the previous operation is not reported as complete yet.

You report orders as complete in the following sessions:

  • Automatic
  • Interactive
  • None

Reporting as completed

Reporting quantities as completed and rejected

Quantities Reported on Previous Operations

This parameter determines when completed quantities on operations are reported.

  • If Completed and Rejected is selected, both quantities completed and rejected are reported for each previous operation.
  • If Completed is selected, quantity completed will only be updated for operations with the Report Product field in the Report Operations Completed (tisfc0130m000) session is set to Automatic.
Note: Rejected quantities are always reported on the operation. When the option Completed is selected, quantities rejected are frozen when the quantity completed is updated.

Operation setting of Report Product in Report Operations Completed (tisfc0130m000) is set to:

  • Automatic for operation 10
  • Manual for operation 20

The Quantities Reported on Previous Operations field in the Production Order Parameters (tisfc0100s000) session is set to Completed.

Quantities reported:

  • Rejects individually per operation
  • Completed are reported for operation 20 only, this updates the completed for operation 10.

  • Completed and Rejected
  • Completed
Allow correcting Operations in Report Orders / Reset Status

the Uncomplete All Operations and Decrease Quantity Operations commands become available in the Report Orders Completed (tisfc0120s000) session and the Reset Completed Orders to Active Orders command in the Reset Production Order Status (ticst0203m000) session.

Calculation Method Remaining Production Time

This parameter determines how the remaining production time is calculated if the production has already started.

If a production order operation is a fixed duration operation, the remaining production time is always calculated based on time spent, because in that case operation lead times are not calculated by using operation quantities.

Allowed values

Planned Quantity

The remaining production time is based on the quantity of the item that must still be processed.

Time Spent

The remaining production time is based on the original production time minus the hours booked on the production order.

Use Reason Codes for Rejected Items

Specifies if and when you must enter a reason code if you reject items when reporting operations complete.

Allowed values

Optional

If this value is selected giving a reason code at rejection of an item is optional.

Mandatory

If this value is selected giving a reason code at rejection of an item is mandatory.

Never

Default value

The default value is Never.

Reporting quantities as completed and rejected

Adjust Planned Receipt for Scrap

Specify when the planned output of an operation is updated after a quantity of items is scrapped.

Note: If Immediately is selected the planned output quantities are adjusted as soon as output is scrapped. This may cause a higher frequency of changes in the planning.

  • Immediately
  • At Operation Completed
Post to Inventory when Reporting on Last Operation

The parameter determines whether the main item must be posted to inventory or not, after the last operation is reported as complete.

In the Report Operations Completed (tisfc0130m000) session the operations are reported as complete.

The field has following values:

  • Yes

    When the last operation is reported as complete the main item is automatically posted to inventory.
  • No

    The main item is not posted to inventory.
  • Interactive

    You are asked whether the main item must be posted to inventory or not. You must select the option either yes or no.

The default value is Interactive.

Label Layout for Printing Labels

If you print labels for completed production orders, the label layout entered in this field determines the format of the labels.

To print labels for production orders, the Print Labels check box in the Report Orders Completed (tisfc0520m000) details session must be selected if you report the production order as complete.

For repetitive manufacturing, the Print Label during Report Orders Completed check box in the Report Production Orders Completed from Production Schedule (tirpt1502m000) session, or the Print Label during Report Orders Completed check box in the Report Production Schedules Completed (tirpt1201m000) session must be selected.

Labels in Manufacturing

Device for Printing Labels

The printer where you print the labels for completed production orders.

Labels in Manufacturing

Allow Alternative Package Definition

the application allows you to use an alternative package definition when products are reported complete.

Note: 
  • By default, this check box is cleared.
  • This check box is displayed only if the Job Shop by Site field is set to Active in the Implemented Software Components (tccom0100s000) session.
Material Settings
Sorting Method Components

The value of this field determines how the components that are included in the materials estimate from the bill of material (BOM) are sorted in the Estimated Materials (ticst0101m000) session.

Note: This sorting order is especially important if you use phantoms.

Allowed values

Item

All components are sorted by item code.

Operation and Item

The components are first sorted by operation (at the highest level) and, subsequently, by item code.

Pos. Highest BOM Level

The components are sorted on the basis of the position numbers from the BOM of the main item.

Own BOM Position

The position numbers from the BOM of the components are used for sorting purposes.

Sequence of estimated material lines

Use of Shop Floor Warehouses

materials for production orders are issued from the job shop warehouse of the work center.

materials are issued directly from the warehouse defined in the bill of material.

Shop floor warehouses

Integrations of JSC with warehousing

Manual Issuing

the materials must be issued by a manual action. If you select this check box, you will have more control over the timing of the material issues.

Note: The value of this parameter does not affect materials that are issued by backflushing or materials that are held as floor stock.

Material issue setup

Overview of material issue

Create Back Order for Warehousing Transfer Orders

and insufficient inventory is available to execute the transfer order to the shop floor warehouse, a back order is generated.

and insufficient inventory is available to execute the transfer order to the shop floor warehouse, you must manually initiate the transfer of the remaining material quantity when material becomes available.

Note: The setting of this check box is not relevant for the issue of materials, only for transfer to a shop floor warehouse.

Defaulted from the Create Backorders check box in the Outbound Order Lines (whinh2120m000) session for outbound order lines for transfer orders with order origin ASC Production.

Shop floor warehouses

Move Allocation to Shop Floor Warehouse

If you are using job shop warehouses, the current parameter determines when the materials are moved to the job shop warehouse.

During production order generation, material is allocated from a warehouse:

  • If the Use of Shop Floor Warehouses check box is selected, this is a job shop warehouse, and the current parameter applies.
  • If the Use of Shop Floor Warehouses check box is cleared, the current parameter does not apply. Material is allocated from the warehouse that is specified in the Estimated Materials (ticst0101m000) session. The default warehouse for this is usually the one that is maintained in the BOM.

The allocated materials are the components specified in the BOM.

Allowed values

At Planning
  • When EP Planned Production Order is created

    The allocations are made on Shop Floor Warehouse
  • When Shop Floor Production Order is created

    The allocations are made on Shop Floor Warehouse
At Generation
  • When EP Planned Production Order is created

    The allocations are made on BOM Warehouse
  • When Shop Floor Production Order is created

    The allocations are made on Shop Floor Warehouse
At Release
  • When EP Planned Production Order is created

    The allocations are made on BOM Warehouse
  • When Shop Floor Production Order is created

    The allocations are made on BOM Warehouse. They will be transferred to Shop Floor Warehouse at the time of release of production order
Not Applicable

Shop floor warehouses are not in use.

Update Method Allocated and Issued Quantities

When the quantity planned input of an operation is adjusted, this parameter determines what happens to the Net Quantity, To Issue and Subsequent Delivery fields of the materials linked to these operations.

This refers to:

  • Material allocations.
  • Materials that have already been issued.
Note: 
  • The materials quantities that have already been issued are displayed in the Actual Quantity field in the Estimated vs. Actual Material Costs (ticst0501m000) session.
  • This parameter only affects materials for quantity-dependent materials.
  • This parameter does not affect cost items.

Allowed values

Allocations and Return Bookings

The reduction of the allocation can exceed the sum of the quantity in the Subsequent Delivery field and the quantity in the To Issue field. In this case, the Subsequent Delivery field is set to zero, and the value of the To Issue field becomes negative. The negative quantity in the To Issue field means that this quantity is posted back to inventory. The value of the Actual Quantity field is reduced by the same quantity.

Only Allocations

The allocation of material is reduced. The Subsequent Delivery field and the To Issue field in the Material to Issue for Production Orders (ticst0101m100) session are reduced by the same quantity. The Subsequent Delivery field and the To Issue field can be reduced to zero but cannot become negative. This condition also limits the reduction of the allocations. Any issued quantities remain unchanged.

Note: While calculating this reduction, the sum of the To Issue field, the Subsequent Delivery field, and the Actual Quantity field is assumed to match the operation's quantity-planned input.
Nothing

The allocations and issued quantities are not affected in any way, not even when the Quantity Ordered field is changed for Created production orders without regenerating the orders ( Update Method in the Production Order (tisfc0101s000) details session is No Action or Recalculate).

Reporting operations as completed

Automatic Select Alternatives

This field determines at which moments LN checks for use-up materials and alternative materials.

Allowed values

  • At Generation

    LN checks for alternatives when a production order is generated.
  • At Release

    LN checks for alternatives when you release a production order.
  • No Automatic Replacement

    LN does not check for alternatives automatically. You can still manually initiate a check for alternatives.
Note: This functionality is available only if the Alternative Materials check box is selected in the Implemented Software Components (tccom0100s000) session.

Searching for alternative materials

Using up remaining stock of outdated items

Check Material Shortages at Release

the Release Production Orders (tisfc0204m000) session offers the option to release only production orders for which no material shortages exist.

Inherit Phantom Operation
If this check box is selected, the feature for phantom materials to inherit the phantom linked operation is enabled.
Hours Settings
Update Method for Estimated Hours

The way in which the estimated hours are updated when the planning is modified.

Allowed values

Automatic

When the planning is modified, the cost estimate is automatically updated.

Interactive

When the planning is modified, you are asked whether the cost estimate must be updated accordingly.

None

The cost estimate is not changed.

Split Hours in Setup and Production

the estimated and actual hours of an operation are split up.

The estimated and actual hours of an operation can be split up in setup time hours and cycle time hours. This results in a setup part and a production part for the estimated and the actual man and machine hours, which can be viewed in, for example, the Estimated vs. Actual Hours Costs (ticst0502m000) session.

Note: Selecting this check box can negatively impact system performance if hours are backflushed. Hours are backflushed if the Backflush Hours check box in the Item - Production (tiipd0101m000) session is selected.
Backflushing
Backflushing Method

Specify the backflushing method.

At Reporting Complete
At Completing Shift
At Closing Work Cell Cost Document
Manual
Backflushing without Warehouse Orders

materials are backflushed without warehouse orders to issue material inventory.

Labor Type

The labor type that is used by LN in non-assembly work centers, if the hours are accounted by backflushing.

Device for Processing Backflushed Hours

The output device for printing the backflushed hours.

Allowed values

The device must have been defined in the Device Data (ttaad3500m000) session.

Backflushing

Device for Issuing Backflushed Materials

The output device for printing the backflushed materials. LN also uses this device to print shortage lists.

Allowed values

The device must have been defined in the Device Data (ttaad3500m000) session.

Backflushing

Documents
Printing Production Order Documents Mandatory

production orders cannot be released before the order documents have been printed.

Note: This parameter does not apply to production orders for repetitive or FAS items.

Printing of documents.

Using order documents

Standard Order Documents
Order Covering Note

the covering note for the production order was printed.

Document Printed

The document has been printed. The data has not changed after the document was printed.

Modified Document

The document has been printed, but the data on the document changed after the document was printed.

Original Document

The original document has not yet been printed.

Using order documents

Routing Sheet

the routing sheet is printed.

Using order documents

Operation Note

the operation note is printed.

This check box indicates the default for the corresponding check box in the Print Production Order Documents (tisfc0408m000) session.

Using order documents

Material List

the material list is printed.

This check box indicates the default for the corresponding check box in the Print Production Order Documents (tisfc0408m000) session.

Using order documents

Collecting backflush materials from the warehouse

Material Issue Note

a material issue note is present.

Subcontracting Note

a subcontracting note is present.

Check List

a checklist is present.

Sawing List

a sawing list is present.

Collective Sawing List

a collective sawing list is present.

Cutting List

a cutting list is present.

Collective Cutting List

a collective cutting list is present.

Receipt Note

a receipt note is present.

Inspection Note

a inspection note is present.

Order Distribution

an order distribution is present.

Instructions
Copy Document Links from Instructions

In the Routing module, you can define a microrouting. You can link documents to instructions in the microrouting by using ODM package.

the documents that are linked to instructions in the Routing module are also available in Job Shop Control .

Print Options
Outbound Data on Material List

outbound data is present on the material list.

Outbound Data on Material Issue Note

outbound data is present on the material issue note.

Storage Conditions on Material Issue Note

storage condition are present on the material issue note.

Using storage conditions

Outbound Data on Checklist

outbound item data is present on checklist.

Using order documents

Contents of order documents

Components Multiple Piece Tools

multiple piece tools are used during the manufacture process.

Serial Number List

serial numbers are selected.

Microrouting on Routing Sheet

one, or more microroutings are present on the routing sheet of the produced item.

Setting up a microrouting

Sequence of Outbound Data

several outbound items are present on the production order.

by Location Sequence No.

The outbound data is printed by location sequence number. You can define a location sequence number for every warehouse location. Location sequence numbers define the most practical sequence of warehouse locations for picking lists.

by Location

The outbound data is printed by location.

Costing
Financial Transactions by Work Center

you can view the production results by work center. The default setting is determined by the Financial Transactions by Work Center checkbox in the Production Order Parameters (tisfc0100s000) session.

WIP transfer

Costing Work Centers

Transfer WIP method

The moment when a WIP transfer takes place.

Allowed values

Always

When a quantity is reported as complete, and the delivering work center is different from the receiving work center, the transfer is performed.

Only upon Completion

When the operation is reported as complete, and the delivering work center is different from the receiving work center, the transfer is performed.

Not Implemented

WIP transfers are never carried out.

Transfer WIP method.

WIP transfer

Process Hours using

To process hours for a production order, labor costs are calculated. To calculate the labor cost, either Estimated Operation Rates or Actual Labor Rates are used.

Allowed values

Estimated Operation Rates

To calculate labor costs, the operation rates defined in the Standard Cost Calculation module are used. The operation rates belong to the work center to the which the hours are posted.

Actual Man and Machine Rates

To calculate labor costs, the employee's hourly labor rate and the machine rate are used.

Actual operation rates.

Moment of Completion Posting

The moment when LN posts the financial transactions for the completed quantities to Financials .

This field can have the following values:

  • Quantity Completed

    Every time you report a quantity of the main item completed, LN posts the corresponding financial transactions.
  • Order Status Completed

    When the production order status is set to Completed, LN posts the corresponding financial transactions.
Note: To limit the number of postings and obtain the best performance, it is recommended to set this field to Order Status Completed, unless you require more frequent posting of transactions.

The default for this field is the Moment of Completion Posting field in the Production Order Parameters (tisfc0500m000) session.

Reporting quantities as completed and rejected

Fallback Calculation Office

If no routing operations are defined for the selected production order, the calculation office specified in this field is used.

A fallback calculation office for production orders is needed if:

  • No routing is defined. Only applicable if the Job Shop by Site parameter in the Implemented Software Components (tccom0100s000) session is set to Inactive.
  • The routing has no operations.
  • The routing has only subcontracting operations.
Posting Method Efficiency Variances per Work Center

Select how calculation office variance and efficiency variances are posted per work center.

Not Applicable

Information on price variances or efficiency variances is not retained for financial reporting. Calculation office variances are posted to the calculation office involved.

On Production Order

The financial transactions relating to price variances or efficiency variances are posted to the production order's calculation office.

On Work Center

The financial transactions relating to price variances are posted to the work center's financial company. This action is only possible if the results are calculated by work center.

Meth. of Posting Price Variances to Work Center

If the Financial Transactions by Work Center check box is selected, you can use this field to determine to which to which financial company the price variances are posted.

Note: The financial company is determined by the enterprise unit to which a calculation office or work center belongs. Calculation offices and work centers are defined as departments, which establish the link with the enterprise unit.

Allowed values

Not Applicable

Information on price variances or efficiency variances is not retained for financial reporting. Calculation office variances are posted to the calculation office involved.

On Production Order

The financial transactions relating to price variances or efficiency variances are posted to the production order's calculation office.

On Work Center

The financial transactions relating to price variances are posted to the work center's financial company. This action is only possible if the results are calculated by work center.

Posting method for price variances.

Posting Method Efficiency Variances on Calculation Office

If the Financial Transactions by Work Center check box is cleared, you can use this field to determine to which financial company the efficiency variances are posted.

Note: The financial company is determined by the enterprise unit to which a calculation office or work center belongs. Calculation offices and work centers are defined as departments, which establish the link with the enterprise unit.

Allowed values

Not Applicable

Information on price variances or efficiency variances is not retained for financial reporting. Calculation office variances are posted to the calculation office involved.

On Production Order

The financial transactions relating to price variances or efficiency variances are posted to the production order's calculation office.

On Work Center

The financial transactions relating to price variances are posted to the work center's financial company. This action is only possible if the results are calculated by work center.

Posting method for efficiency variances.

Posting Method Price Variances to Calculation Office

If the Financial Transactions by Work Center check box is cleared, you can use this field to determine to which financial company the price variances are posted.

Note: The financial company is determined by the enterprise unit to which a calculation office or work center belongs. Calculation offices and work centers are defined as departments, which establish the link with the enterprise unit.

Allowed values

Not Applicable

Information on price variances or efficiency variances is not retained for financial reporting. Calculation office variances are posted to the calculation office involved.

On Production Order

The financial transactions relating to price variances or efficiency variances are posted to the production order's calculation office.

On Work Center

The financial transactions relating to price variances are posted to the work center's financial company. This action is only possible if the results are calculated by work center.

Posting method for price variances.

Use Actual Valuation for
End Item Receipt Posting

end items are received in inventory at their actual costs, and valued according to the defined actual valuation method.

Note: Calculation-office variances can occur for JSC orders with project pegs if planned project pegs deviate from the actual project pegs of the end item. These variances cannot be attributed to price or efficiency.

FTP inventory valuation method is used.

.

Standard and actual cost warehouses

Valuation Prices

Lower of cost or market value

Subassembly Receipt Posting

subassemblies are received in inventory at their actual costs, and valued according to the defined actual valuation method.

Valuation methods are defined in Warehousing .

The actual valuation methods are:

  • Moving Average Unit Cost (MAUC)
  • First In First Out (FIFO)
  • Last In First Out (LIFO)
  • Lot Price (Lot)

Standard and actual cost warehouses

Valuation Prices

WIP Transfers and Completions

the financial transactions of the type WIP Transfer Issue, WIP Transfer Receipt and Completion are logged against actual costs.

Standard and actual cost warehouses

Valuation Prices

Serials
Generate Serial Numbers

Specify when the serial numbers for a schedule line are generated.

  • Manually
  • On Release
As-Built Status Handling

The way how statuses of serialized end items are handled in the Serial End Item - As-Built Headers (timfc0110m000) session.

Allowed values

Automatic

The status handling of serialized items in the Serial End Item - As-Built Headers (timfc0110m000) session is carried out automatically by LN.

Manual

The status handling of serialized items in the Serial End Item - As-Built Headers (timfc0110m000) session must be carried out manually by the end user.

Working with serialized items in Manufacturing

Overview of serialized items

Serialized items in Manufacturing

Only Serialized and Lot-controlled Items in As-built Components

only serialized items and lot-controlled items are displayed in the Serial End Item - As-Built Components (timfc0111m000) session.

non-serialized items and non lot-controlled items are also displayed in the Serial End Item - As-Built Components (timfc0111m000) session.

As-Built components with serialized and lot controlled items.

Overview of serialized items

Serialized items in Manufacturing

Operation Subcontracting
Production Order Reference on Subassemblies

the production order the subassembly belongs to is referenced during subcontracting.

Subcontracting Operations

Block Order Release when Requisition Mandatory

you cannot release a production order that includes a subcontracting operation for which a Purchase requisitions is not yet generated.

Note: 

Generation of a requisition for a subcontracted operation is mandatory if one of the following is applicable:

  • No subcontractor is specified for the subcontracting operation
  • The Requisition Mandatory for Operation Subcontracting check box is selected in the Items - Purchase (tdipu0101m000) session for the subcontracted service item that is used for the subcontracting purchase requisition

Operation subcontracting in Procurement

Blocking Reason for Automatic Blocking

The reason for automatically blocking a subcontracted operation of a production order for which a purchase requisition is generated.

When the purchase requisition is converted into a purchase order, the subcontracting operation is automatically unblocked.

Operation subcontracting in Procurement

Project Pegging
Freeze Material and Operation Pegs

material supply to the operation pegs is frozen.

Project Pegging in Manufacturing

Split Production Order
Allow Production Order Splits

parts of production orders can be split off into new production orders.

Production order splits - overview

Print Order Documents At Order Split

the Print Production Order Documents (tisfc0408m000) is automatically started when an order is split.

Note: Before you can select this check box, the Printing Production Order Documents Mandatory check box must be selected in this session.

Production order splits - overview

Reason Code for Order Split

Select whether or not a reason code must be specified during order split.

  • Never

    No reason code is required.
  • Optional

    You can optionally specify a reason code.
  • Mandatory

    You must specify a reason code.
Note: Only applies if the Log Production Orders and Allow Production Order Splits check boxes are selected in the current session.

Production order splits - overview

Split Order when Reporting Rejected Quantity

a rejected quantity on an operation or production order can be split off instead of rejected.

and a rejected quantity is specified in the Report Operations Completed (tisfc0130m000) or a quantity to scrap is specified in the Report Orders Completed (tisfc0520m000) sessions, you will be asked if the rejected quantity must be split off. If you click Yes, the Split Production Order (tisfc0208m000) session is started in which you can specify the quantity to be split off.

Note: If the Quarantine Inventory check box is selected in the Inventory Handling Parameters (whinh0100m000) session, it is not possible to spilt off orders in the Report Orders Completed (tisfc0520m000) session. Furthermore, you will not be asked to confirm that you want to split off the rejected quantity in the Report Operations Completed (tisfc0130m000) session.

If the Split Order when Reporting Rejected Quantity check box is selected, the rejected quantity is the default quantity to be split off.

Production order splits - overview

Actual Material Costs breakdown for Transfer Postings

Select the aggregation level of the actual materials costs at transfer.

By Operation Only

All actual material costs are aggregated to the operation level before transfer. This lowers the amount of transactions.

Note: If this parameter is selected, price variance per material cannot be calculated properly.
By Operation and Material Position

All actual material costs are transferred separately.

Note: If this parameter is selected, the amount of transactions logged will increase, especially when an operation requires many material components.
Manufacturing Execution System
MES Reporting

the MES Reporting for Job Shop integration has been implemented in the Implemented Software Components (tccom0100s000) session and is available for the selected site.

Note: 

The integration is available if:

  • The Job Shop by Site parameter is Inactive
Reason Codes
Mandatory Reason Production Orders

reason codes for state changes in production orders are mandatory.

Implementation
Transfer Items without Production Orders

items can be transferred from or to the warehouse without the need for production orders.

Change Control
Effective Date

The date production settings changes before effective.

Last Changed by

The employee ID of the employee responsible for the latest change.

Repetitive
Text

additional text is present.

Use Global Repetitive Parameters

the global repetitive manufacture parameters is used for the site. Consequently, changes to product data at company level are synchronized automatically to the site level.

Repetitive Production Schedules
Production Model Series

The production model series used during production.

Series for Manual Schedule Creation

The default series used when manually generating production schedules in Repetitive Manufacturing .

Series for Warehousing Orders

The series that is used to generate warehousing-order numbers.

Series for Work Cell Cost Documents

The default series used for creating work cell cost documents.

Default Operation Rate Code
The operation rate code that is used as default in Repetitive Manufacturing, for each work cell.
Note: This field is displayed only if the Job Shop by Site field is set to Active in the Implemented Software Components (tccom0100s000) session.
Work Cell Cost Document Duration

Specify the duration of the schedule line.

Note: 

The duration can be:

  • Day
  • Week
  • 4 Weeks
  • Month
Generate Serial Numbers

Specify when the serial numbers for a schedule line are generated.

  • Manually
  • On Release
Material Backflushing Method

The value of this field determines the degree of user interaction when backflushing is carried out.

Allowed values

Automatic

Backflushing of materials and hours is carried out automatically in the background when reporting an operation or production order complete, without prompting the user.

Interactive

When you report an operation or production order as complete, a prompt is displayed. You can click Yes to backflush for the completed quantity or click No to skip backflushing. You can backflush manually later.

Manual

Reporting an operation or production order as complete does not trigger backflushing. To backflush separately, you can use the Backflush Materials and Hours (tisfc0220m000) session or batch processing.

see, Backflushing method
Automatic Work Cell Hours

automatic registration and booking of actual work cell hours is active.

Work Cell Hours Method

The method by which the work cell hours are determined.

  • Register Work Cell Hours

    Hours logged by the user.
  • Backflushing Hours

    A theoretical process time based on reported completed and rejected items.
Backflushing without Warehouse Orders

no warehousing orders are created for backflushed material.

See, Backflushing without warehouse orders.

Automatic Labor Hours

automatic registration and booking of actual labor hours is active. The Labor Hours hours in the Report Shift (tirpt4636m200) session are automatically copied and booked to the Actual Labor Hours in the Shift - Hours (tirpt4138m000) session.

Note: Labor hours do not have a method option and are always registered.
Progress Tolerance

The progress of the process variable in percentages.

Report on Work Stations

schedule lines are reported completed at work station and work cell levels.

schedule lines are only reported completed on work cell level.

Note: Reporting completed is mandatory at work stations marked as count points.

Progress Reporting in Repetitive Manufacturing

Work Station Machines
The machine linked to a Work Station.
Repair Process

items can be send for repair during manufacture.

Multi-Product Production

use of production models for multiple end products is implemented.

Production Model

Scheduling Process
Allow Offloading

offloading of planned runs to work cells with later need dates is possible.

Repetitive Production Scheduling

Move and Swap Lines

you can move and swap lines within a run.

Repetitive Production Scheduling

Move and Swap Runs

you can move and swap scheduled runs.

Repetitive Production Scheduling

Offload Runs

selected runs are offloaded to other work cells.

Repetitive Production Scheduling

Assembly
Text

additional text is present.

Use Global Assembly Control Parameters

the global assembly control data is used for the site. Consequently, changes to item data at company level are synchronized automatically to the site level.

Assembly Order Series

The numbers series used for the assembly orders.

Clustered Line Station Order Series

The series used for clustered line station orders.

Line Station Variant Series

The series used for line-station variants.

If the Transaction Processing parameter is Line Station Based, you must enter a value in this field.

Reference Number Series

The reference number series used.

Reference numbers are used in combination with external supply methods. In order-controlled supply in line sequencing (SILS), an unique reference number is generated for every unique combination of line station + VIN number + assembly kit ID.

If internal supply is used, this field remains blank.

Assembly control overview

Effective Date

effective date

Last Changed by

The code of the employee who made the last changes to the parameters.

Tool
Text

additional text is present.

Use Global Tool Planning Parameters

the global tool planning parameters are used for the site. Consequently, changes to tool parameters at company level are synchronized automatically to site level.

Default Refurbish by

The number of uses after which the tool is refurbished by default.

Effective Date

effective date

Last Changed by

The code of the employee who made the last changes to the tool planning parameters.

Effective Date

effective date

Last Changed by

The code of the employee who made the last changes to the repetitive parameters.

Subcontracting
Text

text related to subcontracting is present.

Use Global Subcontracting Parameters

the global subcontracting planning parameters are used for the site. Consequently, changes to subcontracting parameters at company level are synchronized automatically to site level.

Define Order Number By

Order numbers are defined in:

  • Production
  • Procurement
Product Subcontracting
Purchase Order Series

The purchase order series used during product or operation subcontracting.

Operation Subcontracting
Purchase Order Type

The purchase order type used to subcontract products.

Requisition Series
The requisition order series used during operation subcontracting.
Change Control
Effective Date

The date on which changes to the subcontracting parameters become effective.

Last Changed by

The ID of the employee who made the last changes tot he parameters.

Related topics
Multisite overview