Creating Routings and Bills of Material
You can add routings and BOMs to an inventory item, job, estimate job, or production schedule using these methods (click on each for detailed steps):
- Adding Routing/BOM Information with Engineering Workbench
- Adding Routing/BOM Information Manually
- Copying Routings/BOMs
Current Routing/BOM Notes
When creating a routing (that is, set of operations) and BOM (set of materials) for an item, you must define the operations before you can add materials.
Job Routing/BOM Notes
The job routing and bill of material (BOM) are required before you can release a job and post transactions for the job (such as issuing materials to the job or moving its finished supply to inventory).
In addition to the above methods, you can copy the current job routing to a new job when you change the job's status to Released.
Production Schedule Routing/BOM Notes
In some previous versions of CloudSuite Industrial, you were prevented from changing the production schedule item BOM after the system processed a complete or scrap transaction against any release for a production schedule item. Now, provided that no transactions have been posted against that specific release, you can modify the production schedule release routing/BOM using the Production Schedule Release Operations and Production Schedule Release Materials forms, if desired.
After you add routing and bill of material, you can create complete or scrap transactions for the production schedule.