The Compare tab on the Costing Analysis Workbench is used for 
                           comparing costs for costing analysis. A rolled up costing alternative 
                           record can be compared with items' current or standard costs, or with 
                           costs in another costing alternative.
                        
                        
                        To compare costs:
                        
                     
                     
                     
                        - 
                           Open the Costing Analysis Workbench 
                              	 form and select the costing alternative record for comparison.
                           
                        
 
                        - 
                           Click the Compare tab. The selected costing 
                              	 alternative is displayed on the left side of the form.
                           
                        
 
                        - 
                           On the right side of the form, do one of the following: 
                              	
                           
                           
                              
                              
                                 
                                 - To compare the costing alternative with the items' current 
                                    		 or standard costs, specify a BOM type. 
                                 
 
                                 
                                 - To compare with an existing alternative, specify a different 
                                    		 costing alternative. 
                                 
 
                                 
                              
                              
                            
                           
                         
                        - 
                           In the middle of the form, select an item in the grid. Comparison 
                              	 data for the item is displayed on the tabs at the bottom of the form: 
                              	 
                              	
                           
                           
                              
                              
                                 
                                 - The Operations tabs show operations 
                                    		 on the routing for the selected item.
                                 
 
                                 
                                 - The Materials tabs show components 
                                    		 on the single-level bills of materials for the selected item.
                                 
 
                                 
                                 - The Routing tabs show the expanded 
                                    		 bill and routing for the selected item. Click the nodes to expand 
                                    		 each level.
                                 
 
                                 
                                 - The Assembly tab on the left shows 
                                    		 the total final assembly costs for the selected item in the costing 
                                    		 alternative. The Assembly tab on the 
                                    		 right matches the assembly costs on the Item 
                                       		 Costs form, Cost Detail tab if 
                                    		 you are comparing to current or standard costs.
                                 
 
                                 
                                 - The Accumulated tab on the left shows 
                                    		 the total accumulated costs for the selected item in the costing 
                                    		 alternative. The Accumulated tab on the 
                                    		 right matches the accumulated costs on the Item 
                                       		 Costs form, Cost Detail tab if 
                                    		 you are comparing to current or standard costs.
                                 
 
                                 
                              
                              
                            
                           
                         
                        - 
                           You can make additional changes to the costing alternative as needed 
                              	 for your analysis.
                           
                        
 
                     
                     
                     
                        
                        If this analysis is for a costing alternative that did not use a copied 
                           routing, and if your analysis shows that the revised rates are where you 
                           want them, the next step is to roll the rates to current using the Costing Analysis Alternative Roll Costs to Current 
                           form.