Defining Overlapping Operations
You express the overlapping of two operations with an "offset" hours value representing the number of run time hours the previous operation must complete before this operation can start.
For example, suppose Operation 10 starts at 1:00 and has 4 hours of run time. Operation 20 has an Offset of 0.5 hours. This means Operation 20 can begin at 1:30, which is 0.5 hours after Operation 10's run time starts.
The Offset value begins when run time starts. Run time starts after Setup time is complete.
Differences between Scheduler and APS Processing
The planning and scheduling activities process overlapping operations slightly differently. See the Overlapping Operations topics for more information.