Application parameters that support the Late TS Approval background process

These application parameters must be configured to support the Late TS Approval background process:

Application parameter Purpose
approve_expiration_time_unit

Type of time unit used forthe approve_expiration_time_valueparameter.

Default value: 12 (minutes).

The units are:

  • For MILLISECOND value = 14
  • For SECOND value = 13
  • For MINUTE value = 12
  • For HOUR value = 10

Is Not Customer Editable

approve_expiration_time_value

Duration of time before notifying a user that a timesheet is not approved. Units are defined by the approve_expiration_timeunitparameter.

Default value: 5 (minutes).

connect.display.LateTSApproval

Use to display the Late TS Approval tab.

Default value: 0 (false)

portal.ts.enabled

Use to display the TS Benefit Bank, TS Late Submission, and the TS Late Approval tabs in the Infor XM application based on the role of the user.

Default value: false

ts.DlnqntReportBasedOnCutoffs The default value is set to False, if the ts.DlnqntReportBasedOnCutoffs parameter is not set.
ts.DlnqntReportExcludeCurrentPeriod Determines whether to consider the current reporting period as late submission of the timesheet, when the current day is the last day of the current reporting period. The valid values are:
  • True: Excluding the current reporting period.
  • False: Including the current reporting period, if the current day is the last date of the reporting period.

The default value is set to if the ts.DlnqntReportExcludeCurrrentPeriod parameter is not set.

ts.InitDlnqntReportStartDate

This value must be set before the InitDlnqntSubmitReport background process is executed.

Usage 1: For initialization.

The InitDlnqntSubmitReport background processpopulates the alts_delinquent_report table with the late submission periods for each active timesheet user from the given date to one future timesheet period calculated based on the current timestamp.

Default: yyyy.MM.dd

Example: 2012.06.01

Usage 2: For fixing corrupted data in alts_delinquent_report table.

The parameter considers a single date or a date range where the first date is the beginning of the date range and the last date is the final day in the date range of the corrupted data. The background process clears and refreshes all the data for the period from the date specified to the current date,if the parameter considers asingle date.

Format: yyyy.MM.dd,yyyy.MM.dd

The InitDlnqntSubmitReport background process clears and re-populates the alts_delinquent_report table withthe late submission periods for each active timesheet user for the given period.

Example: 2012.06.01,2012.07.01