Splitting putaway tasks using task manager
- Select Task Manager from the RF device Main menu.
- Click Standard. The Task Manager (TM) screen is displayed.
- Specify this information:
- Area
- The area for the tasks. Note: If this field is empty, the application finds tasks for all the areas for which you have permission.
- Task
- The task type to be completed. Note: You must specify as PA – Putaway.
- Press Enter. The Putaway screen is displayed.
- Specify LPN.
- Press Enter. The Putaway Task screen is displayed.
-
Verify the data and press Enter.
The Confirm Put (PA02AS) screen is displayed.
Note: This screen is displayed only if:
- The value is specified in the Minimum required % of LPN quantity field of the Putaway Detail screen.
- The Dimension Restrictions field value is set to None.
-
Specify this information on the Confirm section:
- LPN Qty
- The total quantity of LPN.
- To Qty
- The quantity to be moved to the final location.
- To
- The assigned Pick location as per strategy.Note: You cannot modify this field.
- To (Confirm)
- The Pick Location to be specified for conformation.
-
Press Enter. The specified quantity
is moved to the final To location and redirected to the Confirm
Put (PA02AS) screen. You can move the remaining quantity with LPN
from the staging location to other location based on the putaway strategy.
Note:
- If the Pick location configured with Lose ID is enabled, the specified quantity is moved to the Pick location.
- If the Pick location is not configured with Lose ID is disabled, an error message is displayed.