Entering indirect activities

Supervisors can enter indirect activities for one or more users through the User Attendance screen.

  1. Select Execution > Productivity/Labor > User Attendance. The User Attendance screen is displayed.
  2. Enter the search criteria to select the associates that require an Indirect Activity record.
  3. To retrieve the records, click Search. The Uses Attendance List tab is displayed.
  4. Select the check box next to each associate record that requires the Indirect Activity.
  5. From the Actions menu, select Create Indirect Activity.
  6. The system displays a dialog box that allows you to enter the Start Time and then select from available activity types. Select the indirect activity you want to assign to the selected group of users, and then click Execute.
    Note:  Supervisors can enter an Attendance Key that is not listed on the screen if they need to associate the Indirect Activity to a different day/shift for the associate.