Moving items to final destination through stocker putaway tasks
Once the pallet has been moved to the final PND location, the stocker tasks are made available through Task Manager. A different associate usually performs these tasks.
- 
            Do one of the following:
			 
		  
            
- Press Esc until the Task Manager (T1) screen displays.
 - From the RF device Main menu, select Task Manager.
 
 - 
            Specify this
			 information:
		  
            
- Area1
 - Specify the area or location for the tasks. If this field is blank, the application finds tasks for all areas in which you have permission.
 - Task
 - Select the task to be performed. To select Stock Putaway tasks, specify S. SP – Stocker Put displays in the field. If nothing is selected, non-cherry pick replenishment tasks are sent.
 -  
					                   
					                   
					                    
 - 
            Press 
			 Enter. The first pallet
			 with Stocker Putaway tasks displays. 
		  
            
			             - To accept the tasks associated with the pallet, press Enter. The next STOCKER PUTAWAY (SP) screen is displayed.
 - 
            In the 
			 PLT field, specify the
			 Pallet ID to confirm it. 
		  
            
			             - 
            To accept, press 
			 Enter. The 
			 STOCKER PUTAWAY (TSP) screen is displayed. 
		  
            
			             - 
            To view the first task
			 associated with the pallet ID that was entered, press 
			 Enter. The 
			 STOCKER PUTAWAY (SP2) screen is displayed. 
		  
            
			            Note: To select a task to complete, press C. See the description at the end of this section for more information. - 
            To accept the task,
			 press 
			 Enter. The 
			 STOCKER PUTAWAY (SP3) screen is displayed. 
		  
            
			             - To confirm the To location, specify information in the LOC field.
 - To accept, press Enter.
 - 
            Repeat steps above until
			 all tasks for the pallet are complete. 
		  
            Note: When all cherry pick replenishment tasks are complete for all pallets, a message is displayed.