LFSO 7.1.0.4 resolved issues
Total: 1 issue
----------------
LFSO-4918
Workload generation is getting STUCK when hours of operation is overnight and distribution is Rule-Based
Workload generation for a location is getting stuck when the hours of operation for that location is overnight and the distribution used for workload allocation for any department is rule based.
Outcome
Fixed by adding one day to the closing time so that the overnight shift will be interpreted correctly and the application will be able to create appropriate intervals.
----------------