Schedule the Table Driven Employee Date Range Recalculation Task when RE_CALC_ON_APPROVAL is set to ASYNC . In ASYNC mode, time attestation approvals are queued for background processing by the task. Schedule the task to run at an interval of approximately 1 minute.
- Select .
- Click Add Schedule.
- Select Table Driven Employee Date Range Recalculation Task from the Task Type list.
- Specify the scheduling parameters for the task and click Submit.
- In the Task Schedules grid, click the Parameters button for the task that you just added.
- Specify this information:
-
Batch Size
-
Thread Count
-
Auto Recalc
-
Process Future Balance Dates
- Click Submit.
Note: If the task is not scheduled, PENDING recalculation entries accumulate. Monitor the task to confirm it remains active