Scheduled hours
The Scheduled column (TS_SCHEDULED_HOURS) shows the total number of hours the employee is scheduled to work each day. For example, if the employee is scheduled to work from 17:00 to 01:00, 08:00 is displayed for that day. If the employee is not scheduled to work on a day, then the scheduled hours value is blank.
Not all schedule details are included in the scheduled hours calculation. By default, a schedule detail is included in the calculation if both of these conditions are met:
- The time code is not an LTA (Is LTA flag not selected).
- The time code is not a scheduled break. See below for break definitions.
You can change the default behavior by configuring these localization parameters in config mode:
includeLTA
Determines whether details with LTA time codes are included in the summary calculation. Specify one of these values:
- true: All details with LTA time codes are included in the calculation.
- false: All details with LTA time codes are excluded from the calculation. This is the default.
includeBreaks
Determines whether scheduled breaks are included in the summary calculation. A break is defined as either:
- A schedule detail with a time code that has the Is BRK flag selected.
- A schedule detail with a defined Schedule Optimization activity that has the Paid Activity attribute set to No.
Specify one of these values:
- true: All scheduled break details are included in the calculation.
- false: All scheduled break details are excluded from the calculation. This is the default.
decimalMinutes
Determines whether the scheduled hours value is displayed in time or decimal format. Specify one of these values:
- true: The value is displayed in decimal format (for example, 8.50).
- false: The value is displayed in time format (for example, 8:30). This is the default.
To calculate the scheduled hours, the schedule details are retrieved from the EMPLOYEE_SCHEDULE and EMPLOYEE_SCHED_DTL tables. The minutes are then summed up considering the includeLTA