Regenerating forecasts
You can regenerate a forecast to incorporate new actual data or to clear manual adjustments.
- Select Scheduling > Schedule Optimization > Forecasting.
 - Click Edit for the forecast that you would like to regenerate.
 - Optionally, click the name of the forecast to edit forecast details before regeneration. Then specify this information in the Forecast Properties window:
           
- Name
 - You can specify a new name for the forecast.
 - Forecast Start Date and Forecast End Date
 - You can specify a new start and end date for the forecast period. Note that the forecast numbers for days added to the forecast period using this method are 0 until they are manually specified or the forecast is regenerated.
 - Start Date and End Date
 - You can specify a new start and end date for the historical data used for linear regression forecasts. For other forecast methods, specify any dates.
 - Initial Adjustment (%)
 - Specify the percentage amount by which the historical data for linear regression forecasts is initially adjusted when regenerating the forecast. For other forecast types, specify 0.0.
 
 - Click Regenerate Forecast to regenerate the forecast. Click OK to confirm. 
           Note: If the Forecast Aysnc task is enabled, a message is displayed notifying you that the forecast is being regenerated. Click OK to confirm and close the Forecasting screen. A Workmail message is sent to you when the forecast is completed, which includes a link to open the forecast.The forecast is regenerated and the forecast results are updated.
 - Click Save.