Part 1: Copies for Budget Solicitation
Suppose that:
The Phased view is used. Therefore, there are the following 3 versions: Working, Released by Me, and Released to Me
One level in the hierarchy does not participate in the budget solicitation process. Therefore, there are 4 participating levels
The number of budget solicitation copies is:
(number of versions x number of participating levels) - 1, because the bottom level does not release, so you subtract one Released by Me copy
= ( 3 x 4 ) - 1
= 12 - 1
= 11