MR_PROCESS_VALIDATION_START_DATE

Description:

This registry parameter determines the baseline start date used for the schedule compliance and schedule publish conflict validation that occurs before MR processing. When set to PAYGRP_CUTOFF, the start date for the validation is the cutoff date used for schedule editing in MVS. This is the same as the cutoff date set in the PAYGRP_CUTOFF_DATE registry parameter. When set to CURRENT_DATE, the current date is used as the start date. The validation starts on the date specified in this registry parameter plus the number of days specified in the MR_PROCESS_VALIDATION_OFFSET_DAYS registry parameter.

This start date must match the start date configured for the Short Term Publish task used to publish MRs. For example, if MR_PROCESS_VALIDATION_START_DATE is set to PAYGRP_CUTOFF_DATE, then the Publish From parameter for the Short Term Publish task must be set to Pay Group Cut Off Date.

Valid Values:

PAYGRP_CUTOFF_DATE or CURRENT_DATE

Default Value:

PAYGRP_CUTOFF_DATE

Location:

/system/modules/emvs/mr_ots

Effective:
6.2.4.23