Generating a schedule

  1. Select Scheduling > Multi-view Scheduler > Schedule Template > Generate Schedule.
  2. Select the unit or team for which you want to generate a schedule, in the Unit field on the Unit tab.
  3. Optional. If sub units are used for the Unit, you can include them in the generation. To do so, select the Include Sub Units field. This shows the templates of the selected unit and its sub units. Only selected templates are generated.
  4. Select the time period for the schedule using the Generation Dates fields.
  5. Click Next.
  6. Do one of these options: