Adding shifts to a ST

  1. Display the ST to which you want to add shifts.
  2. Locate the day part to which you want to add shifts.
  3. Click the plus sign (+) icon beside the job under the Shift heading. A row of blank fields is displayed directly below the plus sign (+) row.
  4. Click the menu icon in the Shift column field.
  5. Select a shift from the window.
  6. Specify the number of staff needed for this shift in the Day 1 column field.
  7. Repeat the previous step for each day of the shift.
  8. Click Save.