Running the Schedule Effectiveness Report

  1. Select My Reports > Schedule Optimization Reports > Analysis Reports > Schedule Effectiveness Report to run the report on demand.
  2. Specify this information:
    Location
    Select the location to include in the report.
    Team
    Optionally, select the teams to include in the report.
    Start Date
    Select the start date for the report.
    End Date
    Select the end date for the report.
    Productive Hours Only
    Select this check box to only include productive hours in the report. Some typical examples of non-productive time codes are UAT and MEAL. This option is enabled by default.
    Show Parameters
    Select to show the selected parameters at the top of the report.
    Report FormYesat
    Optionally, select the output format of the report (HTML, PDF, or Excel). The default is HTML.
  3. Click Go to run the report.