Removing self-scheduling shifts from the schedule

You can remove shifts that you have selected from a self-scheduling process from your schedule. Self-scheduling shifts can be removed as long as the process that they were selected from is still open.

  1. Select Self Scheduling.
  2. If there is more than one self-scheduling process open for you, select the process that you would like to use to create your schedule from the Processes drop-down.
    Note: Selecting a different process clears any un-submitted shifts selected from the currently selected process. Ensure that you submit any selected shifts before switching the currently selected process.
  3. Click the shift label for the shift you would like to remove from your schedule.
  4. Click Cancel.
If the shift has not previously been submitted, the shift is immediately removed from your schedule. If the shift has previously been submitted, the removal is validated to ensure that it does not violate schedule rules set up by your organization. If a warning message is displayed, you can click Dismiss to remove the shift from your schedule. If an error message is displayed, it may be required to make other changes to your schedule before you can remove the shift from your schedule.