Activating a Master Rotation

When you are finished creating the shift rotation and labor metrics for every row in the Master Rotation (MR), you can activate the MR. Activation generates the schedule by repeating the shift rotation and labor metrics.

  1. Select Scheduling > Multi-view Scheduler > Master Rotation > Manage Master Rotation.
  2. Click Edit for the MR.
  3. Click the Activate button.
  4. Click Activate to confirm.
  5. The rotation rows are checked for shift overlaps or schedule compliance issues within the same row:
    • If no shift overlaps or schedule compliance warnings or errors are found, the MR is activated.
    • If schedule compliance warnings are found, a dialog is displayed listing the warnings, but the MR can still be activated. Click Activate to ignore the warnings and activate the MR, or click Close to cancel activation and fix the rotation rows.
    • If schedule compliance errors or shift overlaps are found, a dialog is displayed listing the issues. The MR cannot be activated. Click Close to cancel activation. Then, fix the schedule and activate it again.
After addressing any issues found, the MR is activated and the status is updated to UNPROCESSED.
You can now use the date selectors in the Details pane to view the schedule that was generated for different time periods. You can also process the MR to publish the schedule.