What is Lost When You Rebuild Budget Balances?
Any data previously in the budget balances table is lost in the rebuild process, because it is specifically this table that is rebuilt by the process.
Likewise, data previously in the purchase order consumed budget table, and in the purchase invoice consumed budget table is also lost. These two tables provide links from the budget balances to individual lines of purchase orders and invoices. The tables are not fully reconstructed by the rebuild process, as these links are not required for any functional purpose once the purchase transactions have been closed. Only purchase transactions that are still open are re-linked in these tables. This should not cause any problems, but it is important to know, as any audit trail is lost from closed purchase transactions to the budgetary situation.