Running contract value update process
In the
you can report and/or update the values on contracts to an absolute amount or by a given percentage.If retroactive adjustment is allowed, and the contract has already been billed past the adjustment date, an additional line is written to the contract, covering the period from the adjustment date to the last billed date with a value equal to the difference between the two prices. The contract isl then billed forward with the new value and the differences are picked up and billed in the subsequent invoice run. If retroactive adjustments are not allowed, the line is billed at the new value the next time a generate invoice run is carried out.