Line Number
-
The line number of the PPO.
-
Customer Part
-
The code of the customer defined part.
-
Supplier Part
-
The code of the supplier defined part.
-
Required Date
-
The date on which the part is required.
-
Quantity
-
The number of parts required.
-
Unit of Measure
-
The unit of measurement for the part.
-
Ship To
-
The location at which parts must be received.
-
Unit Price
-
The price for each unit of the part.
-
Pricing U of M
-
The Unit of Measure (U of M) for the ordered quantity of the part.
-
Extended Price
-
The total price of the line item.
Extended Price = Unit Price X Ordered Quantity
-
Discount
-
The discount applicable to the proposed PO line item.
-
Net Amount
-
The amount applicable to the proposed PO line item after the allowance and charges are applied.
-
FOB
-
The unique identification code for Free on Board.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
CostCenter
-
The Cost center of the facility for which the purchase order line is configured.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Account Code
-
The unique code of the supplier account.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Item Origin
-
The source from which the item was added to the cart.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Catalog Item
-
The proposed PO line item selected from the catalog.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Category Code
-
The code of the category defined for the item.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Category Description
-
The description of the Category Code.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Project Code
-
The project code of the facility linked to the item. This code can be used for budgeting and project tracking.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Project Element
-
The code of the project element.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.
-
Project Sub Element
-
The code of the project sub element.
Note: This option is displayed only if the Indirect Spend check box is selected on the Customer Implementation page.